STEM Center Project Planned Protocols
- STEM Center Purchase Order Issued September 18
- Construction Meetings Weekly
- College/Contractor Goals intend to ensure:
- Safety of Students
- Purchasing Guidelines are followed
- Expenditures are within Budget
- Classroom Availability for Spring Semester
- Faculty Office Availability during Spring Semester with move planned for May
- To expedite construction and safety, we are asking:
- To Honor Hard Hat Zone
- To dishonor requests for tours
- To discontinue short notice requests to suspend work
- Unless due to an emergency (nap time is not an emergency)
- Testing is planned and therefore requested with advance notice
- To receive 72 hours advance notification if we need to postpone construction for evening or weekend events including faculty and parent association meetings.
- Accommodations:
- Contractor is coordinating “tie-in” work with the first floor during dates and times that the school is not in operation:
- Late shift (3-11)
- Weekends
- Holidays
- Intercession
- Two Dates may require staff displacement 11/26 & 11/28
- Contractor and subcontractors are to wear badges
- There are 7 distinct projects associated with the STEM Center:
- Demolition (College MPAs)
- Center and Classroom Renovations (Major Contractor A)
- HVAC (Donor/Contractor B)
- Fire Alarm (Contractor C)
- Bathroom (Contractor D)
- Data Closet (College N&T Staff)
- Faculty Offices (College MPAs)
- The drafts of the plans for Phase 2 (the combined remaining phases 2-5) were received at the end of September 2008 with plans for review on campus in October 2008.
Page last updated: Thursday, February 5, 2009