ATTENTION RIC STUDENTS: If you can no longer log into RIC email, Blackboard or MyRIC, visit the Student Account Page.

Campus Improvement Projects

Summer 2015 Construction Summary

Parking Lot B Renovation

Location: Parking Lot B

Approx. Start/Complete*

  • Start week of May 25
  • Parking lot ready for use August 15
  • Project complete in October

Campus Impacts**

  • Parking Lot B to be closed for the summer.
  • Pedestrians travelling between east and main campus to use crossings provided.
  • Pedestrians travelling between Parking Lot A and main campus.
  • Cole Rd. through parking lot closed.

Phase III Electrical

Location: College Rd. – Mt. Pleasant to Roundabout

Approx. Start/Complete*

  • Start week of May 25
  • Substantial completion August 15
  • Project complete October

Campus Impacts**

  • Travel on College Rd. may be restricted to one-lane at times.
  • Traffic may need to be detoured through Cole Rd. on occasion.

Adams Library electrical service improvement

Location: Adams Library – electrical room and exterior NW corner, Library road

Approx. Start/Complete*

  • Start mid to late June
  • Project complete by end of 2015

Campus Impacts**

  • There will be some power shutdowns at Adams Library.
  • There will be an excavation in Library Rd.

Roberts Hall HVAC Improvements

Location: Roberts Hall – Mechanical room, Roberts Auditorium, roof

Approx. Start/Complete*

  • Start week of May 25
  • Project complete by end of 2015

Campus Impacts**

  • Roberts Auditorium usage must be coordinated with Capital Projects (no events planned for July and August).

Fogarty Nursing Addition

Location: Fogarty Life Science

Approx. Start/Complete*

  • Start mid-July
  • Project complete summer 2016

Campus Impacts**

  • Hammer throw field will be converted to construction site.
  • Parking lot on east side of Fogarty will be removed.
  • Renovation work inside existing building (noise and coordination)

Career Development Renovation

Location: Roberts Hall – Alumni Lounge to Roberts 100

Approx. Start/Complete*

  • Start late August
  • Project complete in December

Campus Impacts**

  • Limited.
  • Some noise.
  • Work all on interior.

Building 2 Renovation

Location: Building 2

Approx. Start/Complete*

  • Underway
  • Project to be complete by end of June

Campus Impacts**

  • N/A

Building 30 Renovation

Location: Building 30

Approx. Start/Complete*

  • Underway
  • Project to be complete by end of June with exception of cubicles (mid-July)

Campus Impacts**

  • N/A

Mailroom Renovation

Location: Physical Plant warehouse

Approx. Start/Complete*

  • Underway
  • Project to be complete early June

Campus Impacts**

  • N/A

Clarke Science 106 Renovation

Location: Clarke Science 106

Approx. Start/Complete*

  • Start in July/August
  • Complete by end of 2015

Campus Impacts**

  • Limited.
  • Some noise.
  • Work generally limited to work in the room.

Donovan Dining Window Replacement/Rehabilitation

Location: Donovan Dining

Approx. Start/Complete*

  • Start in June
  • Complete by end of summer

Campus Impacts**

  • Coordination with Donovan Dining management will be required as some movement of personnel required to complete the project.
  • Seating within dining area may need to be adjusted depending on where work is occurring.

Miscellaneous ADA Improvements

Location: Sidewalks – various locations

Approx. Start/Complete*

  • Work in June and July

Campus Impacts**

  • Temporary shutdown of limited areas of sidewalk

*Start dates and completion dates are approximate.

**All projects involve some level of noise and general inconvenience. Capital Projects will work with the contractor to minimize both.

Page last updated: June 10, 2015